DECEMBER KEY FIGURES
| | Dec qtr 08 | Sep qtr 08 to Dec qtr 08 | Dec qtr 07 to Dec qtr 08 |
| | $m | % change | % change |
TREND ESTIMATES(a) |
|
Value of work done | | | |
| For the private sector | 11 063.8 | 6.3 | 23.0 |
| For the public sector(b) | 6 283.6 | 3.6 | 21.4 |
| Total engineering construction | 17 361.5 | 5.4 | 22.6 |
SEASONALLY ADJUSTED ESTIMATES(a) |
|
Value of work done | | | |
| For the private sector | 11 221.3 | 6.7 | 27.8 |
| For the public sector(b) | 6 369.7 | 2.4 | 24.3 |
| Total engineering construction | 17 591.0 | 5.1 | 26.5 |
|
(a) Chain volume measures, reference year 2006-07. |
(b) Includes work done by the private sector for the public sector and work done by the public sector. |
Value of work done, Chain volume measures
| Value of work done, Chain volume measures - Trend estimates
|
DECEMBER KEY POINTS
VALUE OF WORK DONE, CHAIN VOLUME MEASURES
TOTAL
- The trend estimate for the value of total engineering construction work done rose by 5.4% in the December 2008 quarter.
- The seasonally adjusted estimate for the value of total engineering construction work done rose 5.1%, to $17,591.0m, in the December quarter.
PRIVATE SECTOR
- The trend estimate for the value of work done for the private sector rose by 6.3% in the December quarter.
- The seasonally adjusted estimate for the value of work done for the private sector rose 6.7% in the December quarter to $11,221.3m.
PUBLIC SECTOR
- The trend estimate for the value of work done for the public sector rose by 3.6% in the December quarter.
- The seasonally adjusted estimate for the value of work done for the public sector increased by 2.4%, to $6,369.7m, in the December quarter.
VALUE OF WORK COMMENCED
- The value of work commenced in the December quarter was $18,727.0m, a fall of 17.5% from the September 2008 quarter.
NOTES
FORTHCOMING ISSUES
ISSUE (QUARTER) | Release Date |
March 2009 | 1 July 2009 |
June 2009 | 1 October 2009 |
ABOUT THIS ISSUE
This publication updates the preliminary estimates released in
Construction Work Done, Australia (cat. no. 8755.0) on 25 February 2009.
CHANGES IN THIS ISSUE
There are no changes in this issue.
SIGNIFICANT REVISIONS THIS QUARTER
Compared with the current price estimates in original terms published in the previous issue of this publication:
- The September quarter work done estimates have been revised upwards by $221.4m. These revisions occurred predominantly in 'Oil, gas, coal and other minerals' in Queensland and 'Electricity Generation and transmission' in Western Australia.
INQUIRIES
For further information about these and related statistics, contact the National Information and Referral Service on 1300 135 070 or Willie Hynd on Adelaide (08) 8237 7646.